Hart Co Schools Transport & Maint Facility, JROTC Range & Multi-Sport Athletic Bldgs Hartwell, GA

New Construction

Status

Bidding Closed

Bid Date2/8/24 2:00pm

Company

...

Location

Hartwell, GA

SCHEDULE OF WORK

The construction phase involves completing these facilities per the Construction Manager’s schedule as follows:

- Hart County Schools Transportation Facility and Maintenance Facility:

Substantial completion for the building is December 2024.

- Hart County Schools JROTC Range Building:

JROTC Building will not start until January 2025 and the completion date will be August 2025.

- Hart County Schools Multi-Sport Athletic Building:

Substantial completion for the building is October 2024.